APPENDIX A  

Capital Strategy 2023/24

1            Introduction

1.1        The CIPFA 2021 Prudential and Treasury Management Codes require all local authorities to prepare a capital strategy report which will provide the following:

 

·         A high level long term overview of how capital expenditure, capital financing and treasury management activity contribute to the provision of services.

·         An overview of how associated risk is managed

·         The implications for future sustainability

 

2            Capital Expenditure and Financing

2.1        Capital expenditure is where the Council spends money on assets, e.g. property/ vehicles that will be used for more than one year. In Local Government this includes spending on assets owned by other bodies and loans and grants to other bodies, enabling them to buy assets. The Council has some limited discretion on what counts as capital expenditure, e.g. assets costing below £10,000 are not capitalised and are charged to revenue in the year.

 

2.2        As at the end of January 2023, the Council has incurred capital expenditure of £1,585,086 and will incur further capital expenditure by the end of March 2023. The Council capital expenditure is summarised below:

 

Capital expenditure

 

2021/22

Actual

2022/23

Estimate

2023/24

Estimate

2024/25

Estimate

2025/26

Estimate

Services

(including Housing)

 

1,103,000

2,007,000

3,364,000

104,000

60,000

Okehampton Transport Hub (see 2.3)

0

85,000

2,500,000

10,870,000

0

Total

1,103,000

2,092,000

5,864,000

10,974,000

60,000

 

 

 

 

 

 

Transport Hub

2.3        West Devon Borough Council has been successful in a £13.4million bid to develop a new railway station and integrated transport hub on the Eastern edge of Okehampton. The plans will see the construction of a brand new, purpose built station and car park, which will be easily accessible from the nearby A30, built at the bottom of Devon County Council’s business park off Exeter Road. The aim is to create an area with facilities for bus connections, cycle links and electric vehicle charging. The Borough Council will be the accountable body for the capital project and the estimated capital expenditure (profiled over the next three financial years) has been included within the Council’s capital expenditure estimates within the strategy. The funding will be provided by the Department for Levelling Up Housing and Communities (DLUHC) and the project will be delivered in partnership with Devon County Council and OkeRail.

 

Housing Projects

2.4        A Housing crisis was declared by the Council at its meeting on the 15th February 2022. The motion to Council contained 15 actions, a combination of direct lobbying, some longer term strategic work streams and bringing into focus work already in progress. The business case for individual projects to proceed to construction will be presented to Council for approval at the appropriate time.

 

Regeneration and Investment Strategy

2.4       The Council has approved a Regeneration and Investment Strategy (Minute        Reference CM72, Council 5th April 2022). To date, Investment Properties           have a value of £19.12 million in aggregate as at 31 March 2022.

 

Overall Borrowing Limit

2.5        In September 2019, Council approved an overall Borrowing Limit (for all Council Services) of £50 million. As at the end of January 2023, the Council’s current level of external borrowing is £27.9m.

2.6        Local Authorities are required to submit a summary of their planned capital spending and PWLB borrowing for the following three years. This is updated on at least an annual basis. PWLB borrowing is permitted for the four categories of regeneration, service delivery, housing and refinancing.

 

 

 

 

 

Governance

2.7      The Head of Finance Practice invites bids for capital funding from all service managers annually on the strict proviso that all bids must go towards meeting a strategic priority. All capital bids are ranked against a prescribed priority criteria which is set out in the bid process. Submitted capital bids are assessed against the categories in each priority. Priority 1 categories include meeting strategic priorities and statutory obligations (e.g. Health and Safety, Disability Discrimination Act etc.) and other capital works required to ensure the existing Council property assets remain open. Priority 2 categories link to good asset management whereby the capital work proposed would either generate capital/revenue income or reduce revenue spending. A capital bid that will enable rationalised service delivery or improvement is also considered a Priority 2 category to meet the Council’s aims and objectives. The final capital programme is then presented to Hub Committee and to Council in February each year.

2.8        All capital expenditure must be financed, either from external sources (government grants and other contributions), the Council’s own resources (revenue, reserves and capital receipts) or debt (borrowing, leasing and Private Finance Initiative). The planned financing of the above capital expenditure is as follows:

Financing of capital expenditure

2021/22

Actual

2022/23

Estimate

2023/24

Estimate

2024/25

Estimate

2025/26

Estimate

Capital Expenditure

1,103,000

2,092,000

5,864,000

10,974,000

60,000

Financed by:

 

External sources (Capital grants, NHB, S106)

607,000

*1,622,000

*3,597,000

*10,870,000

0

Own resources (Capital receipts, Earmarked reserves)

334,000

470,000

1,869,000

10,000

60,000

Net financing need for the year (This is the prudential borrowing required)

162,000

0

398,000

94,000

0

*This includes Government Grant funding from the Department for Levelling Up Housing and Communities (DLUHC) for the Okehampton Transport Hub

2.9        Debt is only a temporary source of finance, since loans must be repaid, and this is therefore replaced over time by other financing, usually from revenue which is known as Minimum Revenue Provision (MRP). Alternatively, proceeds from selling capital assets (known as capital receipts) may be used to replace debt finance. Planned MRP and use of capital receipts are as follows:

 

Replacement of debt finance

2021/22 Actual

2022/23 Estimate

2023/24 Estimate

2024/25 Estimate

2025/26 Estimate

MRP

623,000

647,000

660,000

673,000

696,000

Use of capital receipts

0

0

0

0

0

 

 

3            Treasury Management

3.1        Treasury management is concerned with keeping sufficient but not excessive cash available to meet the Council’s spending needs, while managing the risks involved. Surplus cash is invested until required, while a shortage of cash will be met by borrowing, to avoid excessive credit balances or overdrafts in the bank current account.

 

3.2        The Council is typically more cash rich in the short-term as revenue income is received before it is spent, but cash poor in the long-term as capital expenditure is incurred before being financed. The revenue cash surpluses are offset against capital cash shortfalls to reduce overall borrowing.

 

3.3        As at 31 January 2023, the Council had external borrowing of £27.9 million.

 

3.4        As at 30 September 2022, the Council held £27.9m of Investments.

 

 

4            Borrowing Strategy

4.1      The Council’s main objectives when borrowing are to achieve a low but certain cost of finance while retaining flexibility should plans change in future.

4.2      These objectives are often conflicting, and the Council therefore will seek to strike a balance between cheap short-term loans and long-term fixed rate loans where the future cost is known but higher.

4.3      Projected levels of the Council’s total outstanding debt which comprises borrowing is shown below, compared with the capital financing requirement.

 

 

2021/22

Actual

2022/23

Estimate

2023/24

Estimate

2024/25

Estimate

2025/26

Estimate

Debt at 31 March

28,341,000

27,726,000

27,013,000

26,371,000

25,625,000

Capital Financing Requirement

24,900,000

24,253,000

23,991,000

23,412,000

22,716,000

 

4.4       The Capital Financing Requirement is the measure of the Council’s underlying need to borrow for the capital programme. This has been projected to be £23.9 million for 2023/24. This includes borrowing for           leisure, waste fleet, Kilworthy Park, Housing projects and four investment properties.

5            Investment Strategy

5.1    Treasury investments arise from receiving cash before it is paid out again. Investments made for service reasons or for pure financial gain are not generally considered to be part of treasury management.

5.2    The Council’s policy on treasury investments is to prioritise security and liquidity over yield, i.e. to focus on minimising risk rather than maximising returns. Cash that is likely to be spent in the near term is invested securely, for example with the government, other local authorities or selected high-quality banks, to minimise the risk of loss.

5.3    Money that will be held for longer terms is invested more widely including in collective investment schemes (pooled funds whose underlying assets are company shares, bonds, property etc.). One example of which is the CCLA Local Authorities’ Property Fund in which the Council is invested to balance the risk of loss against the risk of receiving returns below inflation.

5.4    Both near-term and longer-term investments may be held in pooled funds, where an external fund manager makes decisions on which particular investments to buy and the Council may request its money back at short notice.

5.5    Further details on treasury investments can be found in the treasury management strategy (Appendix B).

 

 

 

 

 

 

         Governance

5.6    Decisions on treasury management investment and borrowing are made daily   and are therefore delegated to the Corporate Director for Strategic Finance (S151 Officer) and finance staff (where appropriate), who must act in line with the treasury management strategy approved by Council.

5.7    Semi-annual reports on treasury management activity are presented to the Audit and Governance Committee which is responsible for scrutinising treasury management decisions.

6       Investments for Service Purposes

6.1    Governance

           Decisions on service investments are made by the relevant service manager in consultation with the Corporate Director for Strategic Finance (Section 151 Officer) and must meet pre-approved criteria and limits. Most loans and shares are capital expenditure and purchases will therefore also be approved as part of the capital programme.

 

7         Risk Management and Due Diligence

7.1      The Council accepts there is a higher risk on property investments than with treasury investments. Financial risk will be weighed up against social and economic benefits of the investment. The principal risk exposures include variances resulting in a disruption or fall in income streams, fall in capital value which is either site-specific or due to general market conditions, deterioration in the credit quality of the tenant.

7.2      The Council assesses the risk of loss before entering into and whilst holding property investments/property opportunities by carrying out appropriate due diligence checks and implementing mitigation measures in managing risk:

•           The tenants need to be of good financial standing (this is assessed using Dun & Bradstreet credit rating reports and annual accounts). The number of tenants e.g. sole tenant or multi tenanted will be assessed.

•           The property condition such as date of construction and any imminent or significant refurbishment or modernisation requirements (forecast capital expenditure).

•           How the property investment, financial or non-specified investment meets the Council’s multiple objectives as set out in the Council’s strategy.

•           The lease must meet certain standards, such as being in a commercial popular location and have a number of years left on the lease providing a certain and contractually secure rental income stream into the future. Any break clauses will be assessed along with the number of unexpired years, bank guarantees and rent reviews.

•           The location will be within West Devon Borough Council’s boundary. The population of the catchment area, the economic vibrancy and known or anticipated market demand as well as proximity to travel infrastructure and other similar properties will be assessed.

             Future borrowing from the Public Works Loan Board must meet one of the four permitted categories of borrowing of regeneration, service delivery, housing or re-financing of existing debt.

•           Rental income paid by the tenant must exceed the cost of repaying the borrowed money from the Public Works Loan Board (which is itself funded by the Government). The surplus is then an ancillary benefit which supports the Council’s budget position and enables the Council to continue to provide services for local people. 

•           The gross and net yield are assessed against the Council’s criteria.

•           The prevailing interest rates for borrowing at the time.

•           Debt proportionality considerations.

•           The life and condition of the property is assessed by a valuer and the borrowing is taken out over the life of the asset. The amount of management and maintenance charges are assessed as well as the ease of in-house management. 10% of all rental income (or an amount as deemed prudent) is put into a Maintenance and Management Reserve to cover any longer-term maintenance issues.

•           The potential for property growth in terms of both revenue and capital growth will be assessed.

•           The risks are determined by the property sector e.g. office, retail, industrial, associated with specific properties and the mix of sectors within the Council’s portfolio.

•           Details of acquisition costs e.g. stamp duty land tax, legal costs

•           The documented exit strategy for a purchase/new build.

•           The legal and technical due diligence checks will also identify any specific problems such as anomalies in the title deed, restrictive use classes, indemnities, local competition, construction or refurbishment requirements.

•           The Council engages the use of external advisors to assist in undertaking elements of the due diligence checks such as technical, legal, accounting, property and taxation advice.

 

 

•           The Council undertakes sensitivity analysis of the interest repayments on its borrowing requirements as a percentage of its available reserves to ensure there is sufficient coverage in the event that rental income is below that forecasted. This ensures that the Council has the available reserves to enable service delivery to be maintained in the short to medium term, whilst alternative solutions are implemented.

7.3      Risk of loss shall be assessed on a case by case basis as part of the acquisition due diligence and will be a criteria considered throughout the approval process. Risk of loss during the management phase of the investment shall be reported in accordance with the criteria below. In accordance with Para 23-25 of Statutory Guidance on Local Government Investments, quantitative indicators or risk and portfolio performance will be reported to the Audit and Governance Committee. The frequency of this reporting is anticipated to be every 6 months and will include the following indicators (as applicable):

 

·         Rental value by property

·         Rental value by tenant

·         Sector split by purchase price

·         Purchase price

·         Rental income profile

·         Tenant lease length

·         Gross Yield

·         Management, Maintenance and Risk Mitigation Reserve (MMRM)

·         Current value

 

Governance

7.4       Acquisitions must conform to the adopted Regeneration and Investment   Strategy. Any deviation from the agreed Strategy will require Council           approval. The Council has approved a Regeneration and Investment Strategy   (Minute Reference CM72, Council 5th April 2022).

7.5       The Council’s Senior Leadership Team will initially consider each proposal          as an initial step and recommend that the proposal proceeds in principle.

7.6       The Regeneration and Investment Committee will consider and evaluate (in         accordance with this Strategy) proposals for acquisition of assets on a     case by case basis, and will make any necessary recommendations to the         Head of Paid Service and Section 151 Officer who will make a decision in consultation with the Leader of the Council and Chairman of the Regeneration           and Investment Committee.

7.7       The Council will consider debt proportionality (the amount borrowed to date          against the net service expenditure ratio) on a case by case basis for each         acquisition as part of the decision making process. Investment indicators are     set out within the Council’s Treasury Management Strategy.

 

7.8       The Council undertakes sensitivity analysis of the interest repayments on its        borrowing requirements as a percentage of its available reserves to ensure      there is sufficient coverage in the event that rental income is below forecast. The Council also sets aside 10% annually of all rental income and other     income into a Maintenance, Management and Risk Mitigation (MMRM)             Reserve. This is part of the Council’s contingency arrangements.

7.9       Specialists will be commissioned to act on behalf of the Council to source            suitable properties and manage the acquisition due diligence process.

7.10    Before a final decision is made to proceed with an acquisition, local ward Members will be briefed and be able to share their views with the        Regeneration and Investment Committee.

7.11    Development proposals on Council owned land must also conform to the objectives of the Regeneration and Investment Strategy.

7.12    Unlike investment acquisitions however, they shall not benefit from the same      scheme of delegation.  Instead, approvals must be sought through the Hub      Committee and Full Council process.  Decisions on in area development shall        consider, as appropriate, the views of the local Members and key       stakeholders (Town Council / Parish Council) as one of many aspects of any             projects brought forward. 

Debt Proportionality

7.13    The investment strategy considers the risks of investment and the Council            engaged Treasury Management advisors to analyse the level of debt   proportionality to the Council’s finances (e.g. levels of reserves, asset base      and level of interest costs as a percentage of income).

7.14    Investment Property acquisitions expand the Council’s balance sheet and interest costs will form a higher percentage of locally derived income. It would absorb a high level of reserves if there are shortfalls in or disruption to the income stream required to meet the additional expenditure.

7.15    Sensitivity analysis on the level of debt interest against the Council’s level of reserves is considered as part of the Medium Term Financial Strategy and as part of the budget proposals each year. This ensures that the Council has the available reserves to enable service delivery to be maintained in the short to medium term, whilst alternative solutions are implemented.

7.16    In order that investments remain proportionate to the size of the Council, borrowing for the Regeneration and Investment Strategy is subject to an overall limit (for all Council services) of £50 million.

7.17    The Council set an upper limit on External Borrowing (for all Council services) as part of the Medium Term Financial Strategy of £50 million. Interest payments at 4% would equate to 21.7% of available reserves (Appendix F to the Budget Proposals report for 2023/24 – Council 21st February 2023).

 

Liquidity

7.19    Compared with other investment types, property is relatively difficult to sell and     convert to cash at short notice and can take a considerable period to sell in certain market conditions. To ensure that the invested funds can be accessed when they are needed, for example to repay capital borrowed, the Authority will spread its liquidity profile across its portfolio and also have a spread of the sector in which the Council invests. The Council also documents potential exit strategies as part of its due diligence checks.

7.20    Liquidity will be a factor in determining the amount of rent set aside in the Maintenance Management and Risk Mitigation Reserve for each investment which has a balance in excess of £450,000 as at 31 March 2023. This will be reviewed with the same frequency as the risk reporting procedure set out in the Council’s Commercial Investment Strategy.

8            Asset Management

8.1    To ensure that capital assets continue to be of long-term use, the Council has an asset management strategy in place.

8.2    When a capital asset is no longer needed, it may be sold so that the proceeds,    known as capital receipts, can be spent on new assets or to repay debt.

8.3    Repayments of capital grants, loans to third parties for capital expenditure and investments also generate capital receipts.

8.4    The Council estimates to receive nil capital receipts in the coming financial year as follows:

Capital Receipts

2021/22 actual

2022/23 forecast

2023/24 budget

2024/25 budget

2025/26 budget

Asset sales

0

0

0

0

0

Loans repaid

0

0

0

0

0

TOTAL

0

0

0

0

0

 

9            Liabilities

Governance

9.1       Decisions on incurring new discretional liabilities are taken by Head of                         Practice in consultation with the Corporate Director for Strategic                                          Finance (Section 151 Officer).

9.2       The risk of liabilities crystallising and requiring payment is monitored as part of                the budget monitoring and reported to the Hub Committee quarterly.

 

 

10         Revenue Budget Implications

10.1    Although capital expenditure is not charged directly to the revenue budget, interest payable on loans and MRP are charged to revenue, offset by any investment income receivable. The net annual charge is known as financing costs; this is compared to the net revenue stream i.e. the amount funded from Council Tax, Business Rates and general government grants.

Proportion of financing costs to net revenue stream

 

2021/22 actual

2022/23 forecast

2023/24 budget

2024/25 budget

2025/26 budget

Financing costs

1,333,593

792,822

978,480

977,489

986,200

Proportion of net revenue stream

18.3%

10.2%

11.4%

11.9%

11.8%

 

10.2     Further details on the revenue implications of capital expenditure are included in the Revenue Budget.

Sustainability

10.3    Due to the very long-term nature of capital expenditure and financing, the            revenue budget implications of expenditure incurred in the next few years will         extend for up to 50 years into the future.

10.4    The Corporate Director of Strategic Finance (S151 Officer) is satisfied that the      proposed capital programme is prudent, affordable and sustainable and it is   fully integrated with the Council’s 2023/24 Medium Term Financial Strategy,   Treasury Management Strategy and Investment Strategy and other strategic plans. The Capital Strategy is compiled in line with the requirements of the 2021   CIPFA Prudential Code and 2021 Treasury Management Code. The risks             associated with the Investment Strategy are covered within the Strategy.

10.5    The delivery of the individual capital schemes on the plan is directly linked to       the original approval of the capital project supported by each project having a    project lead who is responsible for the delivery of the project (appropriate skills,            contracting, planning etc.) and the subsequent achievement of the objectives        of that project.

10.6    Members, via the Hub Committee meetings receive quarterly budget monitoring   reports on the Council’s Capital Programme as well as quarterly integrated      performance management reports. Through these updates, which are        driven by the requirement of financial reporting, Members can review and   challenge the delivery of projects and any changes to both the timing and             expenditure of the capital project.

 

10.7    If subsequent to the capital project being completed there are variations to the      income expected to be generated from that asset, this will be reported as a variance in the quarterly budget monitoring reporting and if ongoing will be        included in the following year’s revenue budget proposals.

10.8    The Council’s Senior Leadership Team has oversight for the delivery of and        challenge to the Capital Strategy and Capital Programme.

Affordability

10.9     Affordability is critical in applying the capital strategy and approving projects for inclusion in the capital programme. This is either demonstrated by a report on the project being presented to Hub/Council for approval supported by a business case identifying the expenditure and funding, appraisal of alternative options and the risks and rewards for the approval of the scheme, or by delegated procedures set out within the commercial investment strategy (containing this information).

10.10  All projects need to have a clear funding source. If external funding such as        an external grant is to be used, there needs to be a clear funding commitment.

10.11  Affordability of each project needs to be clear, not only for the funding of the        capital spend, but also to cover any ongoing costs of the operation and      funding of that capital spend.

10.12  Where borrowing is to be used, the affordability is of greater importance and         the affordability has to include the interest costs of that borrowing and the       provision for the repayment of the borrowing (MRP). This repayment is             matched to a prudent asset life and any income streams estimated to fund    this asset must be sustainable.  The rules around the governance of this   borrowing are outlined in the Prudential Code (as summarised above).

10.13  At no stage should the asset value be lower than the value of outstanding            debt unless there is a clear plan to mitigate that shortfall or to sell that asset.

 Risks

10.14  The risks associated with a significant Capital Programme and a significant          level of borrowing can be mitigated through all capital projects being            supported by a business case, having adequate project management and/or    project boards, suitable skills for the delivery of the project, tax planning, cash             flow, clear operational plan for the use of the asset, security and due diligence            on loans and purchases, use of external advice where appropriate, project             contingencies, full tender process and regular and transparent reporting to           Members.

 

 

 

10.15  There are clear links from the capital strategy to both the treasury management strategy, prudential indicators, authorised borrowing limits and the revenue budget. These are also subject to review and oversight by Members at the Audit and Governance Committee and Council. For any new borrowing, and this is a greater risk as the value of borrowing increases, this does increase the Council’s overall liabilities that will need to be repaid in the future.

10.16  In addition, this increases the Council’s level of fixed interest and repayment       costs that it will incur each year. In 2023/24 the borrowing liability is estimated   at £27.0 million with ongoing financing costs of the borrowing of approx.        £1.4m. This is a clear risk that all Members need to be aware of.

10.17  However this risk for assets is mitigated by a robust business case and a   MRP that will repay the borrowing costs over a (prudent) asset life. Any      variations from this are set out in the MRP Policy (section 2.5 of the Treasury Management Strategy). Any variation in expected income is an issue,    however given the wide range of operational assets and different income streams this helps to mitigate this risk.

10.18  As outlined above in the position statement, investment properties have a             different type and level of risk. Risk arises from both variations in income      streams (tenant non-renewal etc.) and from asset values (impact economic    conditions and retail trends etc.). The Council has established a clear strategy, criteria and a governance route for these purchases which has             included member training, second opinion on asset values, due diligence, site    visits,             surveys etc.

10.19  There are risks (and rewards) associated with the purchase of these type of          assets, therefore all Members need to have sight of and understand the risks         and rewards inherent in these commercial investments (development    opportunities).

11         Knowledge and Skills

11.1    The Council employs professionally qualified and experienced staff in senior    positions with responsibility for recommending capital expenditure, borrowing and investment decisions to Members.

11.2    The Director of Place & Enterprise is a Chartered Civic Engineer with 19 years of experience. In addition, the Director of Place & Enterprise holds a MSc in Construction Law.

11.3    The Corporate Director of Strategic Finance (S.151 Officer) is a Chartered Accountant (ICAEW) with 19 years of experience of being a S151 Officer (Chief Finance Officer). In addition, the Corporate Director for Strategic Finance holds a BSc in Mathematics and has previously worked in the private sector for accountancy firms.

 

11.4    The Principal Estates Specialist is a Chartered Surveyor, with over 15 years post qualification experience.

11.5    The Monitoring Officer is a qualified solicitor with over 20 years public sector experience.

11.6    Where Council staff do not have the knowledge and skills required, use is made of external advisers and consultants that are specialists in their field. The appropriate expertise is always resourced in relation to any financial, legal and asset related due diligence required. A list is below of advisers that the Council has used in the past:-

 

·         Link Group – Treasury Management Advice

·         Savills – Property Agents

·         JLL – Property and Technical Consultants

·         Arcadis – Building Surveyors and Engineers

·         Womble Bond Dickinson – Solicitors

11.7    This approach is more cost effective than employing such staff directly, and ensures that the Council has access to knowledge and skills commensurate with its risk appetite.

11.8    External treasury management training (by Link Group) for Members will be carried out every two years to ensure Members have up to date skills to continue to make capital and treasury management decisions. Training was last completed in March 2021 and it is planned that the next session will be carried out in the late Summer of 2023 as part of the Member Induction programme.